Solar process
Project Timeline 6 - 10 WEEKS
- Day 1 Consultation 30min or so depending on how many questions you have.
- 2-3 days after consultation is your site survey where we inspect your roof and service panel. we need access to your garage, attic space and roof.( 45min - 1 hour long )
- Final Agreement is ready after site survey with install 3-4 weeks out from there.
- Permitting takes about 2 weeks
- 3-4 weeks out from installation. Special situtations excluded.
- 1-3 days of installation (most residential)
- 3 business days after install is your city/county inspection.
- 10 business days after your inspection passes you will have NVE install your NET METERING meter
- 10 business days after your inspection is PTO or permission to operate. where we come out turn on the system.